Engen Refinery startup
Wednesday, 17 December 2008
Durban's Engen Refinery, which was temporarily shut down following a fire during
the early hours of 13 November, should be back in full production in early
January.
The process of rebuilding the damaged section of the crude unit where the fire
occurred has progressed considerably faster than expected and is now virtually
completed.
According to Refinery GM Willem Oosthuizen mechanical handover of the restored
section to the refinery's operations division is scheduled to take place on
22 December, just 39 days after the plant was shut down.
"We initially thought the refinery might be closed for up to four months because
of the incident. That changed because we have been able to refurbish two of the
three electric motor and pump sets that were at the centre of the fire. Equally
significant has been the way the refinery team and contractors have rallied to
address the problem with efficiency and dedication.
The rebuild has been handled by a construction and engineering team of about 200
people. This team included 14 welding teams that installed the 10 tons of
structural supports and 1.5km of piping that was replaced.
The scope of work has also included:
- More than 10km of electrical and Instrumentation rewiring;
- Repairing 18 control valves,
- Repairing of 15 pumps and motors; and,
- Painting the new facilities with protective coating (about 1000 square
metres)
In the interim the root cause investigation and analysis aimed at pinpointing
the cause (or causes) of the mechanical failure that caused the fire is nearing
completion. The investigation team included four experts from Engen's Malaysian
parent Petronas and an independent engineer nominated by Engen's insurance
underwriters.
According to Oosthuizen this is a painstaking process that involves scrutiny of
evidence from the fire as well as a comprehensive history of the failed pump
set's performance.
"We expect the report back from this in about a week. That report will then be
submitted to the authorities before the findings can be made public," he
explained.
He adds that Engen will obviously examine the final report in great detail to
identify any additional preventative measures that could be taken. "We have also
already improved several procedures based on the post fire assessment which we
do after any process safety event.
"These assessments highlight the things that worked well, like our fire fighting
efforts that were accurate and the areas where we want to do better like the
speed of communication to our neighbours during the event," he said.
On the issue of air quality during the fire, Oosthuizen said the analysis of
samples taken during and after the fire have been analysed by a specialist
laboratory in Italy and forwarded to a toxicologist nominated by the authorities
to determine whether or not the fire posed any health risk, however temporary,
to our neighbours.
It will then be up to the authorities to release the toxicologist's report.